Our Project
Four Laning of Poondiankuppam to Sattanathapuram (Design Ch. Km 67.000 to Km. 123.800) section of NH-45A (New NH-32) in the State of Tamil Nadu under NHDP Phase-IV on "Hybrid Annuity" basis.
Date of Signing of Concession Agreement: 18.05.2021
| Bid Project Cost | 2120.4 Crs. |
| Appointed Date | 20.01.2022 |
| Construction Period | 730 Days |
| Scheduled Date of Completion | 19.01.2024 |
| Actual Date of Completion | PCC - I - 31.05.2024 & PCC-II – 09.12.2024 |
| O&M Period (Years) | 15 Years |
Utility Shifting Status
| Electrical | Completed |
| PHE | Completed |
| Removal of Encroachment | Completed |
| Tree Cutting | Completed |
Preconstruction Activity
| Camp & Establishment Set up | Completed |
| Casting Yard including gantries | Completed |
| Batching Plant Set up with all equipment | Completed |
Land Acquisition Status
| Total Land Required | 150.36 Ha. |
| Total Land Available | 150.36 Ha. |
| Additional Land Requirement | - |
| Likely availability of remaining land | - |
| Project works Status | Completed |
Major Bridge: 7 Nos. (5 nos. Major Bridge + 2 Nos. Major Bridge cum Flyover)
| Foundation | Pile foundations |
| Substructure | Wall / Circular |
| Superstructure | Girder Type |
Minor Bridge: 26 Nos. (25 Nos. Minor Bridge + 1 no. Minor Bridge cum LVUP)
| Foundation | Open foundations / Pile Foundations |
| Substructure | Wall / Circular |
| Superstructure | RCC Slab / Girder Type |
Flyovers: 12 Nos.
| Foundation | Pile foundations |
| Substructure | Wall / Circular |
| Superstructure | Girder Type |
ROB : 2 Nos.
| Foundation | Pile foundations |
| Substructure | Wall / Circular |
| Superstructure | Girder Type (Composite Girder / BOW String Girder) |
Underpass : 10 Nos.
| Foundation | Open foundations |
| Substructure | Wall type |
| Superstructure | RCC Slab |
Box Culvert : 244 Nos.
| Foundation | Open foundation |
| Substructure | Wall type |
| Superstructure | RCC Slab |
| Foot over Bridge | 1 No. |
| SERVICE ROAD | 48.19 Kms. |
| RCC DRAIN | 33.796 Kms. |
| MAIN CARRIAGEWAY | 56.8 Kms. |
| Total Physical Progress | 100 % |