Our Project

Four Laning of Poondiankuppam to Sattanathapuram (Design Ch. Km 67.000 to Km. 123.800) section of NH-45A (New NH-32) in the State of Tamil Nadu under NHDP Phase-IV on "Hybrid Annuity" basis.

Date of Signing of Concession Agreement: 18.05.2021

Bid Project Cost 2120.4 Crs.
Appointed Date 20.01.2022
Construction Period 730 Days
Scheduled Date of Completion 19.01.2024
Actual Date of Completion PCC - I - 31.05.2024 & PCC-II – 09.12.2024
O&M Period (Years) 15 Years

Utility Shifting Status

Electrical Completed
PHE Completed
Removal of Encroachment Completed
Tree Cutting Completed

Preconstruction Activity

Camp & Establishment Set up Completed
Casting Yard including gantries Completed
Batching Plant Set up with all equipment Completed

Land Acquisition Status

Total Land Required 150.36 Ha.
Total Land Available 150.36 Ha.
Additional Land Requirement -
Likely availability of remaining land -
Project works Status Completed

Major Bridge: 7 Nos. (5 nos. Major Bridge + 2 Nos. Major Bridge cum Flyover)

Foundation Pile foundations
Substructure Wall / Circular
Superstructure Girder Type

Minor Bridge: 26 Nos. (25 Nos. Minor Bridge + 1 no. Minor Bridge cum LVUP)

Foundation Open foundations / Pile Foundations
Substructure Wall / Circular
Superstructure RCC Slab / Girder Type

Flyovers: 12 Nos.

Foundation Pile foundations
Substructure Wall / Circular
Superstructure Girder Type

ROB : 2 Nos.

Foundation Pile foundations
Substructure Wall / Circular
Superstructure Girder Type (Composite Girder / BOW String Girder)

Underpass : 10 Nos.

Foundation Open foundations
Substructure Wall type
Superstructure RCC Slab

Box Culvert : 244 Nos.

Foundation Open foundation
Substructure Wall type
Superstructure RCC Slab
Foot over Bridge 1 No.
SERVICE ROAD 48.19 Kms.
RCC DRAIN 33.796 Kms.
MAIN CARRIAGEWAY 56.8 Kms.
Total Physical Progress 100 %